TRAPEZOIDAL FOOTING FORMULA
Volume, V = (L x B x D) = H/3{A1 + A2 + sq.rt (A1+A2)}
Where A1 = L x B
A2 = l x b
H = D-d (Overall depth of footing – depth of Rectangular footing)
THEORETICAL WEIGHT
Cement = 1440 Kg/Cubic Meter
Steel = 7850 Kg/Cubic Meter
Bricks = 1600 – 1920 Kg/Cubic Meter
1 Horse Power = 745.7 watts
WEIGHT OF ROD/TMT BARS PER METER LENGTH
DIA👇 = WEIGHT PER METER👇
6mm = (6 X 6)/162 = 0.222
8mm = (8 X 8)/162 = 0.395
10mm = (10 X 10)/162 = 0.617
12mm = (12 X 12)/162 = 0.889
16mm = (16 X 16)/162 = 1.580
20mm = (20 X 20)/162 = 2.469
25mm = (25 X 25)/162 = 3.858
32mm = (32 X 32)/162 = 6.321
40mm = (40 X 40)/162 = 9.877
CEMENT REQUIREMENTS
M-10 : 210 Kilogram = 4.20 Bags
M-20 : 320 Kilogram = 6.40 Bags
M-25 : 340 Kilogram = 6.80 Bags
M-30 : 380 Kilogram = 7.60 Bags
M-35 : 410 Kilogram = 8.20 Bags
M-40 : 430 Kilogram = 8.60 Bags
M-45 : 450 Kilogram = 9.00 Bags
M-50 : 450 + M.S 7.5%