PLINTH AREA BASE RATE 2020: C.P.W.D (Central Public Works Department) Govt. of India
👇Budgetary Estimate👇
Sr. No. |
Description | Area in Sq.mt |
Rate Per Sq.mt |
Amount (Rs.) |
A. | Civil works | |||
1 | Construction of new residential bungalow including all Civil work, RCC work, waterproofing, masonry, Plaster, Door, Window, stone/tile flooring, wall tiles, paint, Toilet fittings, pipes, waterproofing, all type of fabrication etc. complete as per C.P.W.D plinth area Specifications Annexure - I (a) R.C.C FRAMED STRUCTURE |
|||
Ground
floor (Floor Height 3.00 Meter) |
108 |
19,700 | 21,27,600 | |
A | Sub Total
Amount (Building Cost) of Part A |
21,27,600 | ||
B. | All type of services | |||
1 | Internal
water supply & sanitary installations: 9 % of building cost |
9% | 1,91,484 | |
2 | Internal
electric installations: 12.5 % of building cost |
12.5% | 2,65,950 | |
B | Sub Total
Amount of Part B |
4,57,434 | ||
C | Total
Amount (Part: A +B) |
25,85,034 | ||
D | Add 1 % QC charges | 25,850 | ||
E | Grand Total
Amount in Rs. |
26,10,884 |
Note: G.S.T charges Extra as per Govt. Norms
PLINTH AREA BASE RATE 2020: CPWD (Central Public Works Department) Govt. of India
https://cpwd.gov.in/Publication/PLINTH_AREA_RATES_2020.pdf
Tags:
Civil Engineering