Budgetary Estimate as per PLINTH AREA BASE RATE 2020: CPWD (Central Public Works Department) Govt. of India

PLINTH AREA BASE RATE 2020: C.P.W.D (Central Public Works Department) Govt. of India



👇Budgetary Estimate👇

 
Sr.
No.
Description Area
in
Sq.mt
Rate
Per
Sq.mt
Amount
(Rs.)
A. Civil works


1
Construction of new residential
bungalow including all Civil work,
RCC work, waterproofing,
masonry, Plaster, Door, Window,
stone/tile flooring, wall tiles,
paint, Toilet fittings, pipes,
waterproofing, all type of
fabrication etc. complete
as per C.P.W.D plinth area
Specifications Annexure - I
(a) R.C.C FRAMED
STRUCTURE




Ground floor
(Floor Height 3.00 Meter)
108
19,700 21,27,600
A
Sub Total Amount
(Building Cost) of
Part A


21,27,600





B. All type of services


1
Internal water supply & sanitary
installations: 9 % of building cost

9% 1,91,484
2
Internal electric installations:
12.5 % of building cost

12.5% 2,65,950
B
Sub Total Amount of
Part B


4,57,434





C
Total Amount
(Part: A +B)


25,85,034
D Add 1 % QC charges

25,850
E
Grand Total Amount
in Rs.


 26,10,884

Note: G.S.T charges Extra as per Govt. Norms


FOR JIGAR DARBAR

PLINTH AREA BASE RATE 2020: CPWD (Central Public Works Department) Govt. of India

https://cpwd.gov.in/Publication/PLINTH_AREA_RATES_2020.pdf